How to Apply for Right of Way Permit
- Type A, B, C and D Permits
- Apply and schedule inspections through www.MyBuildingPermit.com.
 
 
ROW Permit Process
- Type A Permits must apply at least 8 weeks prior to your desired event date. Permit review times may vary between 2 to 12 weeks and are based on the project's complexity
 - Obtain the appropriate application form from the list below.
 - Gather and complete all required materials.
 - Submit the application and required materials using www.MyBuildingPermit.com.
 - Note: Once fees have been paid reviews will begin.
 - If additional information is necessary to complete the review, your application will be returned to you via www.MyBuildingPermit.com along with comments.
 - Once all requirements have been satisfied and your invoice has been paid in full, your permit will be issued along with any special conditions via www.MyBuildingPermit.com.